STATUS UPDATES
UPGRADE COMPLETE
The tie-in of our new generator is complete! We have switched back to utility power without issue.
A few final configuration items remain to complete the automatic transition to generator power, but those will be completed later without operational impact.
Please let us know if you have any questions or concerns – support@datayard.us
Jan 15, 2026 at 12:31 PM EST
UPGRADE NOTIFICATION
Tie-in of our new natural gas generator to our data center has begun. We’ll briefly switch to battery backup power during the tie-in, but no service interruptions are expected. We’ll post an update with any changes or once the work is complete.
Jan 15, 2026 at 10:43 AM EST
EQUIPMENT INSTALL STATUS UPDATE: Electricians are onsite with the DataYard team now, and preparations for the generator tie-in are under way. We’ll post updates as work progresses.
Jan 15, 2026 at 10:10 AM EST
REMINDER: Generator tie-in work will begin tomorrow, 1/15, around 9:00AM. We’ll post updates as work progresses.
Jan 14, 2026 at 1:00 PM EST
EQUIPMENT INSTALL THIS WEEK. This Thursday around 9:00AM, DataYard will tie in the new generator to support our data center. No service interruptions are expected. Additional reminders and updates will be posted later this week.
Jan 12, 2026 at 1:00 PM EST